43rd Street North Preliminary, Detailed Design & Construction Management

​Current Status In Progress​
​Time line Preliminary and detailed design completion Spring 2013​
​Location 43rd Street North from Hwy 3 to 9th Avenue North​
 

PROJECT DESCRIPTION

This project is the preliminary design of 43rd St. N from Highway 3 to 62nd Avenue north and upgrading of 43rd Street North’s 4-lane cross section to a new standard from just north of Highway 3 to 9th Avenue North which will reduce congestion.  

PROJECT UPDATES

January 21, 2013 (weather permitting) – Topographic Survey for week of January 14th was delayed due to weather.  Topographic Survey now scheduled during the weeks of January 21st and 28th.  Work to take place during daylight hours and involve a surveyor collecting topographic features off of the roadway from the CP Rail tracks north to approximately 200 m north of 9th Avenue North as well as down intersecting roadways for approximately 200 m.  On-street survey work is scheduled the morning of January 27th within these same limits. 
 
January 10, 2013 (weather permitting) – Topographic Survey scheduled to begin during the week of January 14th.  Work to take place during daylight hours and involve a surveyor collecting topographic features off of the roadway from the CP Rail tracks north to approximately 200 m north of 9th Avenue North as well as down intersecting roadways for approximately 200 m.  On-street survey work scheduled the morning of January 20th within these same limits.
 
December 20, 2012 – Preliminary Design scheduled to begin in first week of January, 2013
  

BACKGROUND

The City’s north east quadrant has experienced significant industrial and commercial growth. 43rd Street North plays a major role in supporting and sustaining this growth. 43rd Street North is a major truck route and functions as a major arterial roadway carrying traffic volumes up to 14,000 vehicles per day with 10% of these volumes attributed to trucks.
 

SCOPE / DELIVERABLES

Upgrading 43rd Street North’s 4-lane cross section to a divided urban arterial standard from just north of Highway 3 to 9th Avenue North, and upgrading the intersections within this range, will significantly improve the capacity, safety and operations of this major north / south corridor.
 
The preliminary design of the corridor from Highway 3 to 62nd Avenue North will serve to provide the basis for detailed design from Highway 3 to 9th Avenue North as well as the future detailed design(s) from the 9th Avenue upgrade to the City limit at 62nd Avenue North. 
 

OUTCOMES/EXPECTED RESULTS

  • Reduced congestion, queuing & delay on 43rd Street North and its side streets from 9th Avenue
  • North down to Hwy 3
  • Reduced off-tracking at intersections achieved by providing intersection designs which accommodate large double and triple trailer vehicles
  • Improved drainage during major storm events
  • Improved access control on the east side of 43rd Street North south of 9th Avenue North
  • Increased motorist, pedestrian and cyclist safety