About the Project

This project is the construction of Scenic Drive North from 5th Avenue North to Stafford Drive North including:

  • New North to South connection
  • New Softball Valley access road
  • New Waste Water Treatment Plant access road
  • Pedestrian underpass (including mining artwork)
  • Pedestrian pathway connections

Click here for a map of dates for when sections of the roadway will reopen.

Click here for information in the north side Recycling Station.

Project Updates

November 8, 2013 - Official Grand Opening held on November 8, 2013.  

October 25, 2013 - The road will be open to the public on October 30, 2013.

October 17, 2013 - All paving work is complete and the intersection of Scenic Drive and Stafford Drive is open, except for the Scenic Drive southwest bound traffic. The contractor is now focused on pathway construction and the Softball Valley access road. The goal is for the road to be opened to traffic on October 28. The Grand Opening ceremony is set for November 8.

August 30, 2013 - The intersection of Scenic Drive North and Stafford Drive North has reopened to motorists. The southbound Scenic Drive North leg leading to the new construction will remain closed.

July 17, 2013 - deGraaf continues to make good progress on the surface works contract. The installation of the pedestrian underpass artwork is ongoing. Crews are focused on building the Stafford Drive/Scenic Drive intersection. We expect this intersection to be re-opened by the end of August.

June 12, 2013 - As the City of Lethbridge moves to the next phase of the Scenic Drive North project, 9th Avenue North will reopen on June 14th.  On June 25th, the intersection of Stafford Drive/Scenic Drive North will close. The intersection is expected to reopen mid-August 2013.

Click here for a map of the affected area.

April 12, 2013 - deGraaf continues to make good progress on the surface works contract. The shallow and deep utilities as well as the earthworks are all progressing. Work on the Scenic Drive/9th Avenue intersection is ongoing with 9th Avenue estimated to re-open mid June as scheduled. Work also continues on the WWTP and Softball Valley access roads.

March 4, 2013 - On March 11, 2013, there will be a full road closure where Scenic Drive turns into 9th Avenue North. This closure will allow for construction to Scenic Drive North that, once complete, will include a new North to South connection, new road and access to Softball Valley and an artwork-filled pedestrian underpass.

Click here for a map of the affected area.

February 14, 2013 - Earthwork was completed on Friday, December 14. The contract for surface works has started. deGraaf Excavating, the successful bidder on this contract will complete the earthworks, then will move on to underground and shallow utility work, followed by surface work. Shallow utility work along the new Wastewater Treatment Plant access road is in progress.

November 13, 2012 The tender for paving and other surface work has been awarded to de Graf Excavating Limited of Lethbridge.

October 22, 2012 Major earth works is continuing and is expected to be completed by the end of November 2012.

June 22, 2012 The City of Lethbridge started construction on the extension of Scenic Drive North. This new roadway will reduce traffic along Stafford Drive North and 9th Avenue and offer better access to recent developments north of 26 Avenue North. It is expected to be complete in September 2013.

 
Did you miss the Open House? Click here to view the information presented.


May 22, 2012 The City participated in the Traditional Blessing Ceremony lead by Blood Tribe government elders.  Aboriginal_Blessing_Info.pdfAboriginal Blessing Information
 
June 29, 2012 The City hosted a sod turning event with political dignitaries to celebrate the beginning of construction.  

 Sodturning.JPG

The Contractor (Richardsons) is currently filling in the deep, deep, deep coulees.

 

 

June 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/scenicnorth1.JPGJune 2012
June 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/scenicnorth2.JPGJune 2012
June 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/scenicnorth3.JPGJune 2012
June 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/scenicnorth4.JPGJune 2012
October 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 1.jpgOctober 2012
July 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 2 July 2012.jpgJuly 2013
October 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 2.jpgOctober 2012
July 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 3 July 2012.jpgJuly 2013
October 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 3.JPGOctober 2012
October 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 4.JPGOctober 2012
November 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 5.jpgNovember 2012
November 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 6.jpgNovember 2012
December 2012http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 7.jpgDecember 2012
May 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 91.JPGMay 2013
May 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 92.JPGMay 2013
May 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN 93.JPGMay 2013
Aerial view on October 8, 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN Aerial - October 8, 2013.jpgAerial view on October 8, 2013
February 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN Feb 2013.jpgFebruary 2013
July 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN July 2012.jpgJuly 2013
March 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN Mar 2013.jpgMarch 2013
September 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN Sept 2013.jpgSeptember 2013
April 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN1 Apr 2013.JPGApril 2013
April 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN2 Apr 2013.JPGApril 2013
February 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN2 Feb 2013.jpgFebruary 2013
March 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN2 Mar 2013.jpgMarch 2013
April 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN3 Apr 2013.JPGApril 2013
April 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN4 Apr 2013.JPGApril 2013
February 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN5 Feb 2013.jpgFebruary 2013
February 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN6 Feb 2013.jpgFebruary 2013
February 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN7 Feb 2013.jpgFebruary 2013
February 2013http://www.lethbridge.ca/living-here/Projects-Initiatives/Current-Projects/Scenic Drive North Extension/SDN8 Feb 2013.jpgFebruary 2013

 


​Source ​Amount
Alberta Municipal Infrastructure Program (AMIP) ​$14,000,000
Build Canada Fund (BCF) ​$6,000,000
​Total $20,000,000​
 