2013 Roadway Overlays

​Current Status ​Complete
​Timeline ​Summer 2013
​Location ​Various Locations Throughout Lethbridge

 

About the Project

Roadway overlays includes the milling and re-paving of various streets within the City of Lethbridge.
 
Milling is when a grinding machine goes down the total length and width of a street and grinds 60 to 80mm of asphalt off the top of the road surface. The material that is ground off is reused by putting it back into the asphalt mix that is put back onto the roadway. This reused material make up approximately 14 % content in the mix design.

 

2013 Arterial Roadway Overlay Schedule

​Location ​Status
5th Street South (between 1st and 3rd Avenue South) Complete
23rd Street North (between 5th and 18th Avenue North)​ ​Complete
26th Avenue North (New construction to 43rd Street North) ​Complete
28th Street North (between 14th and 18th avenue North) Complete
Scenic Drive South (between 4th Street South and 10th Avenue South) ​Complete
 

 

2013 Local & Collector Roadway Overlay Schedule

​Location ​Status
7th Street North (between 2A and 4th Avenue North)​ Complete
8th Avenue North (between 27th Street North to End of Cul-de-Sac) Complete
8A Avenue North (between 23rd and 27th Street North) Complete
9th Avenue North (between 23rd and 28th Street North)​ ​Complete
13th Avenue South (between 15th and 24th Street South) ​Complete
14th Avenue South (between 15th and 18th Street South) ​Complete
17th Avenue South (between 21st and 23rd Street South) ​Complete
20th Avenue South (between Mayor Magrath Drive South and 43rd Street South) ​Complete
24th Street North (between 8A Avenue North and 27th Street North) ​Complete
24th Street South (between 16th and 19th Avenue South) ​Complete

 

 Funding

​Source ​Amount
​Grant - Basic Capital ​$786,000
​Grant - MSI (Municipal Sustainability Initiative) ​$318,000
​Total ​$1,104,000
 