Cable Replacement Program

​Current Status Completed​
​Timeline 2012​
​Location Various City Locations​
 

About the Project

Underground cable was first installed in Lethbridge in the late 1960's and has performed very well in our operating and environmental conditions. The original cable was expected to have an estimated lifespan of 20 to 30 years but is now over 40 years old. Our operating policies have allowed us to obtain the additional life from the cable but it has reached the end of its practical lifespan. This project will allow us to enter areas with aged cable and replace the entire area at one time. This is a normal function of any aging asset and will be a continuing project for the next 10+ years. The new cable is constructed with improved designs providing an expected lifespan of 40 - 50 years.

 

​Location ​Status ​Map
Winston Churchill ​ Complete Click here​
Park Meadows​ Complete Click here​
Lakeview Complete Click here
​Park Royal ​Complete Click here
​Varsity Village ​Continued in 2013 Click here

 

 

 Funding

​Source ​Amount
​External Borrowing ​$5,513,000
​Total ​$5,513,000
 

 

 

 

Contact Information

Burns Hill, Electric Distribution Manager
City of Lethbridge
403 320 4886