2019 Watermain Renewals

​Current StatusActive
Timeline2019
LocationVarious​ locations

About the Program

Like all infrastructure, pipelines eventually need to be replaced. As our water, sewer and storm lines reach the end of their design life, the likelihood of failure increases. We analyze all pipelines based on a variety of factors including but not limited to; failures, condition, risk, roadway quality, location, and customer feedback. The results of this examination optimize the annual renewal programs. The final step is to coordinate renewals in conjunction with roadway overlays to ensure we are not disturbing new asphalt.

 

Scheduled Renewals

Location​Time Frame (Estimated)

2 Avenue North (Between 13 Street & 14 Street)

​April 1 - April 12
29 Street South (Between 11 Avenue & 12 Avenue)April 15 - May 3
28 A Street South (Between 11 Avenue & 12 Avenue)May 6 - May 24

5 Avenue South (From 24 Street to 27 Street)

24 Street South to 27 Street South (between 5 Avenue and 6 Avenue)

​End of May - Mid August

 

​4 Avenue South (From 23 Street to 27 Street)

24 Street South to 27 Street South (between 4 Avenue and 5 Avenue)

Mid August - End of October
 

To learn more about watermain breaks please click here.

Contact Information

Adam Campbell, Water & Wastewater Operations Manager
City of Lethbridge
403-320-4744