Sign In

3 Avenue South Reconstruction (D-22)

Project Status Design
Project Type Transportation
Timeline 2017 - 2020
Budget (sources)  
Expenditures to Date  
Budget Status  


Links

Project Map

Click here to view 2018-2027 CIP D-22

About the Project​

The City of Lethbridge is excited to be embarking on a redesign and reconstruction project for 3 Avenue South. Planned changes will upgrade underground infrastructure and improve access, traffic efficiency and safety making it a more vibrant and pedestrian friendly street.​

Based on the important work of past planning studies, this project will focus on streetscaping (bringing together all elements that give a street character and make it functional for residents). Streetscaping looks at things like lighting, seating, paving materials, and plants/trees. 

This project provides the preliminary design of the streetscaping and underground infrastructure on 3 Avenue South between Scenic Drive and Stafford Drive, followed by the detailed design of the same on 3rd Avenue South between 4th Street South and 8th Street South (see attached project map). 

Completing community consultation and detailed design will prepare the project for the construction phase which can be completed when additional funding becomes available. 
  

Past Engagement

June 21, 2017 from 2-6 p.m. at Casa
View project design and ​begin a community discussion on the stages of construction.​


Funding

​SourceAmount
City of Lethbridge$2,630,000
​Federal Gas Tax Fund​$2,000,000
MSI Grant​$5,453,000

Total

​$10,083,000

Contact Information

Crystal Scheit, Project Manager
City of Lethbridge
crystal.scheit@lethbridge.ca
403-320-3902