Crossings Branch Expansion and Enhancement (D-26)

Project Status Warranty/Deficiencies
Project Type Facility
Timeline August 2019 - start of detailed design
June 2020 - phase 1 project start-up
August 2020 - phase 1 project end date
2021 - substantial completion
Budget (sources) $1,050,000.00
Expenditures to Date $174,000.00
Budget Status On Budget

​About the Project

This project includes two distinct phases.  The first phase includes an upgrade to the ventilation system to keep the library cool during the summer months.  This phase has been approved within the 2018 to 2021 timeframe of the Capital Improvement Program (CIP).  The second phase includes a functional expansion of the Crossings Branch into the adjacent undeveloped space of 2588 square feet.  The second phase is scheduled to begin design in 2022.

Project Updates

September 2020

The project is substantially complete.

June 2020 

The project is in the construction phase.  This phase will be completed by August 2020.

September 2019

A consultant is currently engaged to recommend how the existing ventilation system can be upgraded to provide additional air conditioning capacity.  Projected construction start date is early 2020.


Links

Funding

​Grant - Federal Gas Tax Fund (FGTF)​$191,000.00​Construction Services
​Grant - MSI Replacement Program​$838,000.00​Consulting Services, Equipment & Furnishings, Other
​Other​$21,000.00​Consulting Services
​Total​$1,050,000.00

 