Sign In

Legacy Park Additional Amenities - Picnic Shelter (D-27)

Project Status Warranty/Deficiencies
Project Type Parks
Timeline • May 2018 – project start
• June 2019 – tender for construction
• Spring 2021 – estimated completion
Budget (sources) $1,549,663.00
Expenditures to Date $1,146,520.00
Budget Status On Budget

About the Project

The Picnic Shelter facility will have heated barrier-free washrooms, a food prep kitchen area, wood-burning fireplace, BBQs, griddle and an outside covered picnic area for public events and gatherings.  This facility will be fenced off and be a rentable facility.

​Project Updates

December 2020

The project is in the warranty/deficiency phase and should be complete in early 2021.

October 2020

The project continues to be in construction. 

July 2020

The project continues to be in construction. 

October 2019

This project is currently in construction.   The facility is scheduled to be substantially complete in spring of 2021.

 

Links: 

 

 

Funding

 

​Grant - Federal Gas Tax Fund (FGTF)$1,100,000​Design and Construction
​Grant - Municipal Sustainability (MSI)$449,663​​Design and Construction
Total$1,549,663

 

Contact Information

Rob Villeneuve, Facility Services
Project Manager
rob.villeneuve@lethbridge.ca