About the Project
Construction of an additional 7000 ft2 on the tipping floor to provide additional efficiencies in the sorting and storage of waste materials.
Project Updates
June 2022
The roof and wall cladding systems are being installed; the concrete slabs are being poured.
March 2022
Structural steel is complete.
December 2021
Foundation work is complete.
September 2021
The construction contract was awarded to Ward Bros Construction.
Spring to Summer 2021
Re-scope and reissue the construction Request for Quotation (RFQ).
December 2020
The Request for Quotation (RFQ) submissions received for project construction were over budget so the RFQ was cancelled. The project will be re-scoped and a new RFQ will be reissued in January/February of 2021.
August/September 2020
Value engineering.
June/July 2020
Request for Quotation issued.
June 2020
Phased design complete.