Sign In

Waste Transfer Station Upgrades (E10)

Project Status Design
Project Type Waste & Recycling
Timeline 2017 - Ian Moxon Arch selected as design consultant
2018 - planning and conceptual design
June 2020 - complete design, select contractor
Spring 2021 - start construction
Fall 2021 - operational
Budget (sources) $3,120,000.00
Expenditures to Date $512,531.86
Budget Status On Budget

​About the Project

 

 

Construction of an additional 7000 ft2 on the tipping floor to provide for additional efficiencies in the sorting and storage of waste materials.

Project Updates

December 2020

The Request for Quotation (RFQ) submissions received for project construction were over budget; therefore, the RFQ was cancelled. The project will be re-scoped and a new RFQ will be reissued in January/February of 2021.

August/September 2020

Value engineering.

June/July 2020

Request for Quotation issued.

June 2020

Phased design complete.

 

 

Funding

​Borrowing Utilities$​2,920,000​Construction
​Borrowing Utilities​$200,000​Consulting
​Total​$3,120,000

 

Contact Information

Jace Adams, Facility Services
Project Manager
jace.adams@lethbridge.ca