Sign In

Waste Transfer Station Upgrades (E10)

Project Status Design
Project Type Waste & Recycling
Timeline 2017 - Ian Moxon Arch selected as design consultant
2018 - planning and conceptual design
June 2020 - complete design, select contractor
August 2020 - start construction
Summer 2021 - operational
Budget (sources) $3,120,000.00
Expenditures to Date $512,531.86
Budget Status On Budget

​About the Project

 

 

Construction of an additional 7000 ft2 on the tipping floor to provide for additional efficiencies in the sorting and storage of waste materials.

Project Updates

August/September 2020

Value engineering.

June/July 2020

Request for Quotation issued.

June 2020

Phased design complete.

 

 

Funding

​Borrowing Utilities$​2,920,000​Construction
​Borrowing Utilities​$200,000​Consulting
​Total​$3,120,000

 

Contact Information

Jace Adams, Facility Services
Project Manager
jace.adams@lethbridge.ca