Wastewater Treatment Plant Biosolids Treatment Upgrades E-13
Page Content
Status | Active |
---|
Timeline | 2018 - 2019 |
---|
Location | Wastewater Treatment Plant |
---|
About the Projects
Modification of previous CIP project E-15 of 2014-2023. This project was included in the prior CIP at $6.2 million. The change in budget is due to a modification to the project’s scope , resulting in a cost reduction of $4.2 million.
The two existing Wastewater Treatment Plant digesters were constructed in 1987. A third digester was previously believed to be required to allow periodic maintenance. Implementation of new technology will allow more efficient use of the existing digester capacity and eliminate the need for a third digester.
This project will implement additional biosolids dewatering equipment and upgrade existing biosolids digester process control.
Purpose & Justification:
This project will:
Increase performance,
Improve reliability,
Improve operator health and safety, and
Support continued growth and development of the City.
Funding:
Borrowing-Utilities | $2,000,000 |
---|
| |
---|
Total | $2,000,000 |
---|
Contact Information
Doug Kaupp, Manager - Water, Wastewater & Stormwater
City of Lethbridge
403 320 3078
Links
Click here to view 2018-2027 CIP E-13