Current Status | Completed |
---|
Timeline | August 6 -November 23, 2018 (weather permitting) |
---|
Location (Map) | 13 Ave N (15 St - 23 St N) 23 St. N (13 Ave - 11 A Ave N) 10 Ave N & 20 St. N |
---|
About the Project
The City's first watermain lining project will kickoff on August 6 and take approximately 15 weeks. Analysis of these watermains identified a need to rehabilitate them. Lining the mains is a lower-impact alternative to digging and replacing them.
Timeline:
- August 6 - 20: Temporary Water Installation
- August 20 - September: Dig Access Pits
- September-November: Line Watermains
Watermain Lining Process