Sign In

North Lethbridge Watermain Lining

​Current StatusCompleted
​Timeline​August 6 -November 23, 2018 (weather permitting)
​Location (Map)

​13 Ave N (15 St - 23 St N)

23 St. N (13 Ave - 11 A Ave N)

10 Ave N & 20 St. N

About the Project 

The City's first watermain lining project will kickoff on August 6 and take approximately 15 weeks. Analysis of these watermains identified a need to rehabilitate them. Lining the mains is a lower-impact alternative to digging and replacing them.

Timeline:

  • August 6 - 20: Temporary Water Installation
  • August 20 - September: Dig Access Pits
  • September-November: Line Watermains

 Watermain Lining Process

 

 

Contact

Jeremy Charlesworth, C.E.T.
Project Technologist
403-380-7313
jeremy.charlesworth@lethbridge.ca