West Lethbridge Operations Depot Phase 2 (D-5)

Project Status Construction/Warranty/Deficiencies
Project Type Facility
Timeline October 2018 - started construction
June 2019 - completed construction
Budget (sources) $3,630,000.00
Expenditures to Date $1,797,097.00
Budget Status On Budget

About the Project​

This three-phase project involves the construction of a facility in west Lethbridge to address the future needs of Public Operations.  Phase 2 is the construction of a wood-frame, arch-rib, sand/salt storage facility.

 

 

 

 

 

 

 

 

 

 

 

 Links

Funding

​Grant - Municipal Sustainability Initiative (MSI)​$4,730,000.00​Construction Services
​PAYG - Community​$400,000.00​Consulting and Construction Services
​Total​​$5,130,000.00

 

Contact Information

Ric Johnston, Facility Services
Project Manager