Current Status |
Completed |
Time line |
All civil work to be completed in 2017 |
Location |
Along 26 Ave N from Scenic Dr to 43 St |
---|
About the Project
To free up space in the 26 Ave corridor by putting two overhead lines underground.
Schedule
Construction throughout the summer and fall of 2017.
Funding
Distribution Extension Annual Program (F-14) |
$5M |