Sewer Lining

​Current StatusOngoing
​Location

Downtown
3 Ave. S.
Stafford Dr. N.

About the Project

This project is part of the planned sewer maintenance program. Inspections in 2014 identified corrosion in the 70+ year-old-pipes. Analysis identified a need to rehabilitate the sewer lines and that relining is a lower-impact and lower-cost alternative to digging and replacing them. During the lining process a bypass piping system is setup that will run 24/7.

 Stafford Drive Lining - Overall Map.pdf


Overall Schedule:
March 20 - April 30, 2019 
Although there was a change in start date due to a delivery delay, the revised dates are now posted.

​Location​Dates​Map
​Stafford Dr. N. Between 2A - 5 Ave. N.
​March 29 - April 3, 2019Stafford Drive Lining - Phase 1.pdf
​Stafford Dr. N. Between 5 - 7 Ave. N.
​April 7 - 15, 2019Stafford Drive Lining - Phase 2.pdf
​Stafford Dr. N. Between 7 - 9 Ave. N.
​April 21 - 27, 2019 Stafford Drive Lining - Phase 3.pdf
​3 Ave. S. Between 5 - 7 St. S.
Note: no impact to sewer; lane reductions only
​April 4 - 6, 2019
3 Ave S - Lining Map.pdf 


The sewer line to some properties in these areas will be temporarily blocked for up to 8 hours while the lining is installed. Please avoid activities such as flushing the toilet, showering/bathing or washing laundry/dishes as this will cause a sewer backup. Advance notice will be given on exact dates and times of lining work that will impact your property.

Interested in receiving updates about this project? E-mail jeremy.charlesworth@lethbridge.ca

  

The Relining Process

 


Funding

​Source​Amount
​Utilities Capital$2.3 million​
  

Contact Information

Jeremy Charlesworth
Water & Wastewater Project Technologist
403-380-7313
jeremy.charlesworth@lethbridge.ca