Several parking stalls being added to 6 Street Downtown
Starting today, April 29, there will be a series of partial and full road closures on 6 Street South, between 5 Avenue and 4 Avenue, to allow for the addition of new on-street parking stalls.
Crews will first remove the concrete pad, that had previously been used for transit bus passengers, on the east side of 6 Street just south of 4 Avenue. They will then re-pave the area for up to eight new parking stalls.

The work is anticipated to be completed by Tuesday, May 6, weather permitting.
Local access will be permitted for the businesses throughout and letters were delivered, alerting them to the work.
Motorists can anticipate the following impacts:
- April 29 to May 2: Partial closure northbound, with through traffic still allowed
- May 2: Brief full closure of the road, then back to partial closure
- May 2 to May 5: partial closure northbound, with through traffic still allowed
- May 5: Full closure on 6 Street between 5 Avenue and 4 Avenue while paving is underway, then back to partial closure
- May 6: Road fully re-open
Stay safe, follow signs and reduce speed
Please maintain safe distance from all excavated areas and machinery while work is in progress. As crews and contractors work to upgrade and maintain the streets and roads, motorists are asked to slow down and pay attention to signage to keep crews and themselves safe.
Stay up-to-date on road work, detours and closures
Road closures and repairs are available on the City’s WebMap for further information. The WebMap is a dynamic online platform designed to enhance accessibility and streamline information for residents. The map provides residents with accurate and up-to-date information on road closures, facility closures and City projects and initiatives.
More information and other FAQs on City of Lethbridge parking is available here.
Contact Us
City Hall
910 4 Avenue South
Lethbridge, AB T1J 0P6
Phone: 311
or 403-320-3111 (if outside of Lethbridge)