Next stage reached in Whoop-Up Drive repairs
Starting at 9 a.m. Thursday, November 20, the south lane of westbound Whoop-Up Drive will start taking traffic while continuing repairs will temporarily close the middle westbound lane.
This is the latest stage of the major repairs – which remain on schedule – under the Whoop-Up Drive bridge, as outlined in a November 7 update.
The north lane westbound remains open to traffic.

The repairs will follow this schedule, weather permitting:
- November 10: Erect shoring towers under the bridge. Botterill Bottom Road South will be closed to the public for the duration of all repairs. Completed
- November 12 – 18: Repair girder 3 (under lane 3). Current traffic measures remain in place. Completed
- November 20 – 27: Repair girder 2. Lane 2 will close and lane 3 will reopen. This maintains two westbound lanes. When this repair is complete, all three westbound lanes are open.
- November 28 – December 10: Repair girder 4. Lane 4 remains closed. When this repair is complete, all three eastbound lanes are open.
- December 10 – 12: Repair girder 1. No lane closures are required for this repair
Work is scheduled on weekdays from 7:30 a.m. to 7:30 p.m. Based on this schedule, all repairs are expected to be completed by Friday, December 12.
On August 6, a flatbed trailer carrying heavy equipment hit the bottom of the bridge, damaging four of six steel girders. Two were badly damaged. The repairs required extensive planning and coordination.
The repairs involve minor traffic impacts and all speed limits that were implemented on October 10 will remain unchanged for the duration of this work. The weight reduction also remains in place for westbound traffic.
For Public Inquiries:
Call or chat 311 | Monday to Friday, 8 a.m. to 4:30 p.m.
Contact Us
City Hall
910 4 Avenue South
Lethbridge, AB T1J 0P6
Phone: 311
or 403-320-3111 (if outside of Lethbridge)