Development Activity Summary

The Development Activity Summary is a detailed breakdown of the City of Lethbridge’s development permit timeline from the previous year.

2022 Statistics

A total of 1,586 development permits were approved in Lethbridge in 2022.

Of those permit applications:

  • 30% were approved on the same day they were received
  • 31% were approved between 1-3 days
  • 26% were approved between 4-10 days
  • 8% were approved between 11-25 days
  • 5% took more than 25 days to approve

The average time for development permit approval in Lethbridge was 6 days.