Energy efficiency requirements are part of the residential and commercial building permit processes in Alberta. These requirements address the energy performance of building components and systems, including the building envelope, insulation, windows, doors, heating, ventilation, cooling and service water heating.

Residential projects must comply with the National Building Code - Alberta Edition (NBC-AE). Commercial projects follow the National Energy Code of Canada for Buildings (NECB).

This page explains the compliance options and identifies the documents you need to submit with your building permit application.

Commercial Building Requirements

For applicable commercial and industrial building permit applications, submit the NECB Project Summary with your application. Supporting calculations and additional information may also be required.

The NECB was developed to improve the energy efficiency of Canadian buildings. It covers a range of building components and systems, including the building envelope, electrical systems and mechanical systems.

Residential Building Requirements

Residential building permit applications must comply with the applicable energy efficiency requirements of Section 9.36 of the NBC-AE.

There are three compliance paths available. You must select one for your building. This will affect the calculations, drawings and supporting documents required for your application. Multiple compliance paths cannot be combined on a single building.

The prescriptive path involves meeting the applicable requirements for building envelope assemblies and building systems set out in Sections 9.36.2 to 9.36.4 of the NBC-AE.

Your drawings and supporting information must demonstrate that the proposed components meet the required performance values. Additional drawings or details may be needed to show continuity of insulation and the air barrier at joints, transitions and changes in building assemblies.

This path is generally suitable when the proposed design meets the applicable prescriptive requirements without needing trade-offs or energy modelling.

The trade-off path allows certain building envelope components to compensate for other components that do not meet the prescriptive values, subject to the limitations of the NBC-AE.

For example, a design may use different insulation or window performance values while demonstrating compliance through the required calculations.

Trade-off compliance requires:

  • All information required for the prescriptive path
  • Completed trade-off calculations using the 9.36 Trade-off Calculator
  • Clear identification of the building envelope areas included in the calculations on the submitted drawings

Trade-offs are subject to specific restrictions. For example, building envelope components must be compared using the permitted categories and equivalent areas, and window-to-window trade-offs must be on the same building elevation.

The performance path uses energy modelling or calculations to compare the proposed building with a reference building constructed in accordance with the NBC-AE.

The proposed design must demonstrate that its calculated energy use is equal to or less than the target energy use of the reference building.

Your submission must include the required modelling information, energy use results, software details and supporting report. The modelling software must meet the requirements outlined in the NBC-AE and the 9.36 Project Summary User Guide.

This path offers greater design flexibility but requires more detailed technical documentation.

How to apply

  1. Select a compliance path
  2. Complete the 9.36 Submittal Form
  3. Prepare drawings and supporting information
  4. Submit all documents with your building permit application
  5. City review

Frequently Asked Questions

If your building permit application is subject to Section 9.36, include the completed form with your submission, along with the required supporting documentation.

No. The City's 9.36 Project Summary User Guide states that only one compliance path may be selected for a building.

The requirements depend on the compliance path you select. Trade-off compliance requires trade-off calculations. Performance compliance requires energy modelling information and a supporting report. Prescriptive compliance requires information and drawings demonstrating that the applicable Code requirements are met.

The City may request additional information. Missing forms, calculations, drawings or modelling reports may delay the review of your building permit application.